Bravo Mattress Factory
City:
Cape Town
Area:
Epping
Client:
Metropolitan
Value:
R 6,500 000
Duration:
2 months
Completion:
2014
Size:
8,000m²
Scope of Work:
Removal of existing asbestos roof sheeting, cladding & rainwater goods.
New roof sheeting.
New side cladding.
New rainwater goods.
New fire & ventilation system.
Removal of existing asbestos roof sheeting, cladding & rainwater goods.
New roof sheeting.
New side cladding.
New rainwater goods.
New fire & ventilation system.
As this is a production facility the work had to be completed within 6 weeks during the annual festive holidays.
Multiple teams were deployed to work on various fronts so that the work could be completed in time and it was.
Multiple teams were deployed to work on various fronts so that the work could be completed in time and it was.