Cape Town International Airport

City: Cape Town
Client: Airports Company SA
Value: R40 000 000
Duration: 20 months
Completion: 1 May 2010
Size: 55 000m²

Scope of Work:
- Roof covering to the new terminal, parking garage, elevated roadway and passenger bridges.
- The installation of permanent formwork was also included.

Challenges:
This project was undertaken whilst the airport remained operational. A large portion of the work had to be done on the airside with the work being carried out daily between 01h00 – 04h30. Installing the over purlin insulation over a twenty-metre void was done without any safety incident.